Ministry of Finance has frittered away billions


Inspectors found that the Treasury Department violated the Law on Public Procurement. Had signed a five amendments to the contract for the supply of Integrated Information System of the Treasury (IISSP) without previously announced tender. Made the same mistake resort also for other contracts in 2010.

In addition, the Department also violated the law on budgetary rules. Last year, pay suppliers IISSP two advances totaling almost 249 million crowns for a period longer than three months.

Under the law, while one quarter of the maximum possible duration for which a state organizational unit to provide backup. Resort addition of these advances - namely 159.7 million crowns - nevyúčtoval the end of the financial year, as required by law. Payment of such advances was not properly annotated even in the final account of the Ministry.

Intention to create a Treasury Government approved in February 2005. Envisaged that the system will start in 2010 and its acquisition will not cost more than 2.4 billion.The term comprehensive commissioning gradually - through several amendments to the contract - shifted by three and a half years on the 1st July 2013.

Doubly increased and planned expenditures for the construction of the Treasury - from 2.4 to 4.8 billion, among other things, to extend its functionality, and the inclusion of the costs of operation and maintenance.

Was this article: 10 | 8 | 6 | 4 | 2 | 0




Zobrazit sloupec 
Moner | ISIN database | Weather forecast
Česká verze
Kurzy.cz - Akcie cz, kurzy měn, forex, zlato.
Favorite: Prague Stock Exchange Czech crown Czech economy Commodities Gold Trademarks Prague Weather

Copyright © 2000 - 2017

Kurzy.cz, spol. s r.o., AliaWeb, spol. s r.o.,

ISSN 1801-8688